Rosmorport, the state port enterprise under the Federal Agency for Marine and River Transport (Росморречфлот), has begun dredging in the seaport of Korsakov on Sakhalin: the plan is to remove some 1.5 million cubic metres of soil from the water area and the access channel, bring depths to the design mark of 11.4 m and open the port to ships with a draft of up to 9 m, the Ministry of Transport of Russia and PortNews reported. The work sits inside the Logistics Technopark (Korsakov Port) project and is to run until 2029.
Two new vessels do the job, both built in 2026 and delivered to the Sakhalin branch at the end of September: the non-self-propelled cutter suction dredger Korsakovets and the support vessel Moneron. Korsakovets, project JLCSD6000, cuts soil at depths of up to 20 m at 6 thousand cubic metres an hour; length 54.5 m, beam 10 m, draft 2.5 m, a crew of three, seven days of autonomy. Self-discharging hopper barges carry the soil to an underwater disposal site, while Moneron (project JLWB1600, two 601 kW engines, a 2.5-tonne crane, a 15-tonne winch pull) tows the dredger, lays anchors and moves crew and materials.
The work is split into two stages: first the operating water area of the Fish Port and its access channel, some 0.66 million cubic metres, then the water area of the Southern cargo district, some 0.84 million cubic metres. The design documentation cleared both the state environmental expertise and Glavgosekspertiza, and the schedule follows the environmental restrictions of the district, hence 2029.
Modernisation of the port has been under way since 2024; it is described as a link of the Trans-Arctic Transport Corridor, and the throughput of the sea cargo front is being brought to 4 million tonnes a year, PortNews wrote in August. The governor of Sakhalin Region, Valery Limarenko, then promised to finish the whole complex by the end of 2028 and to hand over the upgraded berths of the Fish Port in 2026, with a berth front of up to 790 m and turnover of up to 600 thousand tonnes a year. The two dates, 2028 and 2029, do not agree: dredging outlives the promised completion by a year.
Korsakov carries the main volume of container cargo from the mainland to Sakhalin and the cargo-passenger line to the Kuril Islands. Until the design depth exists a large tonnage ship cannot enter, and the cargo is shared between smaller vessels and neighbouring ports. With 11.4 m available, part of the flow can arrive directly.