Chinese New Year 2027: deadlines for importers

Chinese New Year 2027 falls on 6 February, with official holidays 5–13 February. Factories close early, so importers should plan orders, payments and shipments now.

3 min read Source: VED from Tochka Bank

Chinese New Year 2027 falls on Saturday, 6 February; official holidays run from 5 to 13 February. Factories will start closing before the holidays end, so an importer sourcing from China should plan three things now — orders, payments and shipments — otherwise part of the deliveries will slip into March.

Orders

If the production cycle takes 45 days or more, place the order this week; if about 30 days, by 1 December. Run the final factory inspection no later than 10 January: defects found after 25 January cannot be reworked before the holidays, and the work moves to March.

Payments

Pay all seasonal invoices by 20 December, because Chinese companies close their financial year at the end of the year and tighten compliance. A transfer via an agent takes 7–10 days instead of the usual 2–3. The last payment date for shipments before the holidays is 25–30 December. In Russia, banks and currency control work on a reduced schedule from 1 to 10 January, so payments sent after New Year may be delayed by a week and a half. If the goods are ready and waiting at the factory warehouse, the last payment date is 15 January; later, the supplier may not have time to prepare the goods and export documents. 3 February is the last payment date: Chinese banks suspend payment processing from 5 February, transfers sent 2–4 February may arrive only after the holidays, and payments from 5 to 13 February may hang until 15 February.

Shipping

The last supplier shipments with guaranteed transport booking are 20–25 January. Sea freight: book a vessel slot for a January departure by 10 December — free slots may be gone by early December, and containers in Vladivostok may wait longer than usual for port handling in January. Rail and road: the last trains and trucks leave by the end of January; queues are possible at the border, including at Zabaykalsk and Kazakhstan, so add 1–2 weeks to normal delivery times: by rail — 14–22 days, by truck — 25–35 days, by sea — about a month, by air — 7–12 days.

The importer's free calendar collects Chinese holidays for two years ahead: importer calendar.

What it means for your calculation

Duty, VAT and fee rates do not change, but timing and payments affect the cost of a batch and working capital: a two-week shipping delay means two weeks of frozen money, and a transfer via an agent with commission and exchange rate changes the actual cost of the goods. The calculator does not include these costs; account for them separately when planning the purchase.

Source: VED from Tochka Bank