Chinese New Year 2027: when production stops and what happens to shipments

Chinese New Year 2027 falls on 5 February, but factories slow from mid-January and production recovery stretches into March. What this means for shipments and how to plan.

3 min read Source: Business practice in China

Chinese New Year 2027 falls on 5 February by the lunar calendar, and the official holidays run from 5 to 13 February, with working Saturdays on 31 January and 14 February. For an importer, another date matters more: factories start slowing from mid-January, when workers head home, and full production recovery often drags into early March.

The "Business practice in China" channel reminds readers of the practical consequence: after 25 January logistics within China becomes noticeably more expensive, and goods made to order from mid-January are only taken into production with release at the end of February. From 29–30 January staff go on leave, sales managers rush to close as many orders and prepayments as possible before the holidays, and their promises on deadlines and quality should be taken with a grain of salt.

In January, defect rates, mis-sorting, errors in shipping documents, logistics costs, the number of shipment postponements to March and banking delays all rise. Factories rush production to ship before the holidays, so quality and document control must be strengthened in advance. According to logistics operator Seko, factories in northern China plan shutdowns from 25 January to 15 February, while in southern China downtime can reach three weeks before the holidays and two weeks after; local practice often starts holidays a week before the festival and returns to normal work after the Lantern Festival on 20 February.

Ocean freight is also under pressure: exporters accelerate shipments, carriers introduce additional blank sailings, and peak demand for capacity falls in the weeks before the holidays. Seko recommends booking space at least four weeks ahead, while Maersk advises confirming the supplier's production calendar, booking January sailings before the Christmas holidays and checking which sailings from mid-February to mid-March will actually run.

The practical takeaway is simple: do not wait until mid-January. By the end of November to early December, agree four dates with the supplier — the last day for taking orders, the last production day, the last day goods are ready and the first working day after the holidays — and work back from them. Pre-shipment inspection is best done in early January, and documents should be prepared before offices and services go on holiday. If the cargo is needed in February, it makes sense to decide in advance what goes by sea and what by air, and keep a buffer stock in case sailings are cancelled.

What it means for your calculation: lead times and costs for shipments from China from mid-January to March 2027 become unpredictable, so the cost calculation for a batch should include not only freight but also the risk of delay, reshipment and quality inspection.

Source: Business practice in China